Date: 20100528
Docket: T-2579-91
Citation: FC 2010 588
Ottawa
,
Ontario
, May 28, 2010
PRESENT: Madam Prothonotary Roza Aronovitch
BETWEEN:
ROGER SOUTHWIND, FOR HIMSELF,
AND ON BEHALF OF THE MEMBERS OF
THE LAC SEUL BAND OF INDIANS
Plaintiffs
and
HER MAJESTY THE QUEEN
IN RIGHT OF
CANADA
Defendant
and
HER MAJESTY THE QUEEN
IN RIGHT OF
ONTARIO
Third Party
REASONS FOR ORDER
[1]
The Moving Party, Her Majesty the Queen in Right of Canada (
Canada
), brings a motion to extend the time for the issuance and service of
Canada
’s third party claim against Her Majesty the Queen in Right of Manitoba (
Manitoba
).In response,
Manitoba
maintains that the Federal Court does not have jurisdiction to entertain this third party claim and, in the alternative, that
Canada
has not met the criteria that would warrant an extension of time to issue its claim.
[2]
On the standard enunciated by the Federal Court of Appeal in Hodgson v. Ermineskin Indian Band No. 942, [2000] F.C.J. No 2042 (F.C.A.), namely, whether it is plain and obvious that the Federal Court does not have jurisdiction in respect of the proposed third party claim, I have concluded that it is not plain and obvious.However, neither party addressed the applicable standard in the context of this motion and if that is not the standard to be applied, for the reasons below, I would in any case have found that the Court has jurisdiction.
Background
[4]
The underlying claim by the plaintiffs, Roger Southwind, for himself and on behalf of the Lac Seul Band of Indians, is for compensation for damages to reserve lands and infrastructure arising out of the construction of a dam and subsequent flooding of Lac Seul.The following is the relevant background.
[5]
Canada
,
Ontario
, and
Manitoba
are signatories to the 1928 Lac Seul Storage Agreement (the Agreement).It provided for the construction of a dam on Lac Seul, in north-western
Ontario
, to store water for use in generating hydroelectric power (the Project).
Ontario
would construct the dam and bear two fifths of the capital costs of the Project,
Canada
would bear the remaining three fifths.The Agreement was ratified by and made a schedule to the federal Lac Seul Conservation Act, 18-19 George V, c. 32 (LSCA) and the Ontario Act Respecting Lac Seul Storage, 18 George V, c. 12.
[7]
The MNRTA was ratified by
Canada
by the Manitoba Natural Resources Transfer Act, 20-21 George V, c. 29 and by
Manitoba
by the Manitoba Natural Resources Transfer Act, C.C.S.M., c. N30.The MNRTA, section 8 of which is the basis of
Canada
’s third party claim against
Manitoba
is a Schedule to both Acts.The MNRTA was ratified by the Parliament of the
United Kingdom
by the Constitution Act, 1930 (formerly British North America Act, 1930), 20-21 George V, c. 26 (
U.K.
) and as such, forms part of the Constitution Acts, 1867 to 1982.
[8]
Pursuant to s.8 of the MNRTA,
Manitoba
, after the coming into force of the MNRTA, was to pay the sums which “have been or shall hereafter be expended by
Canada
” pursuant to the Agreement which had been ratified by the LSCA.Thus,
Manitoba
became responsible for
Canada
’s share of the capital costs of the Project.
[9]
The generating station served by the Project began operation in 1930. The plaintiffs claim that in July 1934, the lake level was raised to five feet above its highest natural level, and that in August 1938, it was further raised to ten feet above its highest natural level.
[10]
Canada
admits that the increase in the lake level had the effect of flooding and damaging the plaintiffs’ reserve lands and improvements thereon. The plaintiffs claim that the flooding made part of the reserve into an island and submerged other parts. In addition, the plaintiffs claim that the “
Traditional
Territory
” was flooded and damaged. This refers to land surrendered by the plaintiffs but over which they retained certain hunting and fishing rights pursuant to Treaty no. 3 that was entered into by
Canada
and the plaintiffs in 1874. The geographical area of the
Traditional
Territory
and the exact nature and scope of the plaintiffs’ rights there are disputed between the parties.
[11]
On November 25, 1942,
Canada
and
Ontario
negotiated a settlement of their respective claims arising from the Project. They agreed to a $72,539 compensation package for the plaintiffs. After other debts were offset, $50,263 was deposited to the plaintiffs’ capital trust account on November 17, 1943.
The Underlying Action
[13]
The plaintiffs allege that
Canada
breached its fiduciary duties, Treaty no. 3, and the Indian Act, R.S.C. 1985, c. I-5, in authorizing the Project without taking adequate steps to protect the plaintiffs, and in failing to adequately compensate them.
The Proposed Third Party Claim
[15]
The definition of “capital costs” includes “compensation for timber, buildings and improvements, including . . . Indian Lands . . . taken or in any way injuriously affected in connection with the proposed work.”
Canada
alleges that the plaintiffs are claiming compensation for Indian Lands injuriously affected by the Project. Therefore, at least part of the damages awarded will be “capital costs” for which
Manitoba
is liable.
History of This Action and the Specific Claim
[16]
The plaintiffs filed a specific claim though
Canada
’s Specific Claims Process on September 24, 1985. The Statement of Claim in this action was issued on October 9, 1991 based on the same facts that underlay the specific claim.
[17]
On May 26, 1995,
Canada
accepted the specific claim for negotiation. Accordingly, by Order dated December 8, 1998, this Court exempted the present action from rule 380 of the Federal Courts Rules, SOR/98-106 (the Rules), which had the effect of suspending these proceedings while the specific claims process was ongoing.
[18]
In a letter dated August 15, 2003,
Canada
invited
Manitoba
to participate in its negotiations with the plaintiffs on the specific claim and later that year, on October 23, 2003, provided
Manitoba
with relevant historical documentation. In a further letter dated December 29, 2003,
Canada
advised
Manitoba
of the Federal Court action and requested that
Manitoba
agree to a “standstill agreement,” whereby limitation periods would not run.
Manitoba
did not agree to a standstill agreement, but a third party claim was not commenced.
[20]
By Order dated November 28, 2008, the Court ordered that the Federal Court action continue as a specially managed proceeding.The plaintiffs thereafter issued an amended statement of claim on February 24, 2009.
Canada
filed its statement of defence on June 30, 2009, the date that its third party claims should have been issued.
Canada
did not issue the claims in time, ultimately resulting in this motion to extend time.
The jurisdiction of the Federal Court over the proposed third party claim
[21]
The parties cite ITO—International Terminal Operators Ltd. v. Miida Electronics Inc. (1986), 28 D.L.R. (4th) 641 (S.C.C.) at page 650, (ITO) for the following elements that are necessary to found Federal Court jurisdiction:
1. There is a statutory grant of jurisdiction by Parliament.
2. There is an existing body of federal law essential to the claim.
3. The law in question is a “law of
Canada
” within the meaning of s.101 of the Constitution Act 1867.
[22]
Admittedly, Section 17 of the Federal Courts Act, R.S.C. 1985, c. F-7 is not a grant of jurisdiction for claims made by the Crown in right of Canada against the Crown in right of a province, (Lubicon Lake Indian Band v. Canada (1981), 117 D.L.R. (3d) 247 (F.T.D.)), section 19 of the Federal Courts Act and Manitoba’s Federal Courts Jurisdiction Act, C.C.S.M., c. C270, however, grant the Court jurisdiction over “controversies” between Manitoba and Canada.
[23]
Manitoba
submits that section 19 of the Federal Courts Act is not sufficient to grant jurisdiction as in its view that there is no “controversy” in this case.The province says that s.8 of the MNRTA requires it to pay sums expended by
Canada
pursuant to the Lac Seul Storage Agreement, but none of the plaintiffs’ alleged causes of action are related to the Agreement. Instead, they relate to
Canada
’s independent obligations under Treaty no. 3, the Indian Act, and common law fiduciary duties. For that reason, there is no live controversy over whether
Manitoba
has failed to meet its obligations under the MNRTA.
[24]
Manitoba
further submits that there is no body of federal law essential to the third party claim, which is a separate proceeding from the underlying action. The third party claim is founded in contractual indemnification under the MNRTA, which is a contract between
Canada
and
Manitoba
; thus subject to provincial law of contract.
[26]
With respect to
Manitoba
’s argument that there is no “controversy” in this case, the definition of “controversy” in s.19 of the Federal Courts Act was considered by the Federal Court of Appeal in The Queen (
Canada
) v. The Queen (P.E.I), [1978] 1 F.C. 533.Le Dain J., as he then was, held as follows at paragraph 67:
The term "controversy" is broad enough to encompass any kind of legal right, obligation or liability that may exist between governments or their strictly legal personification. It is certainly broad enough to include a dispute as to whether one government is liable in damages to another.
[27]
Canada
’s third party claim for indemnity and
Manitoba
’s position that it does not have an indemnity obligation in respect of the damages claimed, in my view, is a dispute between governments which falls squarely within Justice Le Dain’s definition of “controversy.”
[28]
As to whether the second and third branches of the ITO test are met, the Federal Court of Appeal in Fairford First Nation v.
Canada
(Attorney General), [1996] F.C.J. No. 1242 (Q.L.) (Fairford) (CA), expressed doubt that any substratum of federal law beyond s.19 of the Federal Courts Act is required to give the Federal Court jurisdiction. The Court took the view that s.19 provides a complete grant of jurisdiction and suggested that the second and third branches of the ITO test need not be considered where s.19 applies.
[29]
Canada
also referred to several other cases to argue that s.19 is unique, that controversies under s.19 are fundamentally different from disputes that rely on provincial contract law.In Ontario v. Canada, [1909] S.C.J. No. 28 (Q.L.), the Supreme Court of Canada held that the predecessor to s.19 requires courts to decide claims on some legal or equitable ground. It dismissed
Canada
’s claim against
Ontario
for not disclosing any such ground.The Supreme Court suggested in its judgement that had a contract or quasi-contractual agreement existed between
Canada
and
Ontario
, that may have provided a ground on which the Court could have found in
Canada
’s favour.Further support for the view that s.19, on its own, grants the Federal Court jurisdiction to hear disputes involving agreements between governments.
[30]
While the views of Federal Court of Appeal as expressed in Fairford (CA) are sufficient to conclude that the Court has jurisdiction to decide the third party claim, if an additional substratum of federal law is necessary, one exists in this case. First, the main claim rests on federal aboriginal law.
[31]
Second, and more to the point, Canada claims an indemnity against Manitoba for amounts awarded to the plaintiffs that are “capital cost”, as set out in the Lac Seul Conservation Act, that are moreover payable by Manitoba pursuant to s.8 of Manitoba Natural Resources Transfer Act, both federal statutes and federal law within the meaning of the ITO test.S.8 on which
Canada
rests its claim and which
Manitoba
says is purely contractual, has no independent standing, and can not be severed from the federal law which gives it effect.
[32]
Put another way, it may be said that the “contract” ratified by federal statute, is thereby a “legislated contract” which derives its force from the statutes that give it affect and validity, and is therefore federal law: Cree Regional Authority v. Canada (Federal Administrator), [1991] 3 F.C. 533 (F.C.A.).
[33]
It is therefore not plain and obvious that there is no jurisdiction in this Court over the proposed third party claim.
Extension of time to issue a third party claim against Manitoba
[34]
The parties are ad idem that to secure an extension of time, an applicant must meet the test set out in Canada (A.G.) v. Hennelly, 244 N.R. 399 (F.C.A.) (Hennelly), and answer to the following factors, not all of which have to be established in any particular case.In applying Hennelly, the Court must consider whether the applicant can show a continuing intention to pursue the claim; whether the claim has some merit; whether prejudice to the responding party arises from the delay; and finally, whether there is a reasonable explanation for the delay.
[36]
Before discussing the factors, the following further facts are relevant to the delay in issuing the third party claim. As noted above, this proceeding came under case management on November 28, 2008.On February 2, 2009, an order issued, on consent, granting leave to the plaintiffs to amend their statement of claim, which was then issued on February 24, 2009.
[37]
A timetable was set for the exchange of affidavits of documents and the close of pleadings.
Canada
was due to file its defence on May 31, 2009.On June 15, 2009, the plaintiffs provided a status report to the Court. They indicated they would consent to an extension of time for
Canada
to file its defence, and mentioned that
Canada
had advised them of its intention to bring a third party action against the
Province
of
Ontario
and Ontario Power Generation.Thus, with the consent of the plaintiffs, the Order of February 2, 2009 was varied on June 22, 2009, to give
Canada
until June 30, 2009 to file its defence.
[38]
That same order of June 22, 2009 provided that
Canada
was to advise the plaintiffs as to how it intended to proceed with its third party claims, and requested the availability of the parties for a case conference.
Canada
believed that a case management conference would be scheduled in early September 2009, and that jurisdictional issues would be addressed at that time.
[39]
In essence,
Canada
wished to bring third party claims against
Manitoba
,
Ontario
, and Ontario Power Generation.The Federal Court would likely not have jurisdiction over Ontario Power Generation, and the Ontario Superior Court would not have jurisdiction over
Manitoba
without
Manitoba
’s consent.This called for consultations and securing consent, if possible.
[40]
A case conference was fixed for September but had to be adjourned due to the unavailability of counsel.In the interim, on September 28, 2009,
Canada
served draft third party claims on
Manitoba
and
Ontario
, and asked
Manitoba
if it would consent to the jurisdiction of the Ontario Superior Court.
[41]
The case management conference was held on October 6, 2009.
Canada
was directed to file a “game plan” relating to how it would proceed with respect to the various parties sought to be impleaded.To that end,
Canada
consulted with
Manitoba
on a variety of occasions.
[42]
In an e-mail dated November 26, 2009,
Manitoba
confirmed that it would not consent to be added as a party to the litigation.
Canada
understood that it would not be possible to transfer the action to the Ontario Superior Court. Accordingly, on December 16, 2009,
Canada
filed the present motion for an extension of time to add
Manitoba
as a third party to the Federal Court action.
Canada
also made a motion on December 7, 2009 for an extension of time to add
Ontario
as a third party to the Federal Court action.
Ontario
consented.An order issued on consent on January 8, 2010, extending time to serve a third party claim on Ontario, without prejudice to Ontario’s defences.
[43]
The first of the Hennelly factors to be considered is that of
Canada
’s continuing intention to commence third party proceedings against
Manitoba
.The test in that regard is whether the intention arose before the expiry of the relevant time period, being June 30, 2009, and continued thereafter:Tait v.
Canada
(Attorney General), 2009 FC 1278. It is clear from the Order of June 22, 2009, by which
Canada
was obligated to advise the plaintiffs how it would proceed with its third party claim, that
Canada
’s intention to implead
Manitoba
arose prior to the expiry of the time limit for so doing and continued thereafter.I am satisfied that at the relevant time
Canada
had, and continues to have, the requisite intent.
[44]
In the circumstances, I also find the explanation for the delay to be reasonable.Time was needed to obtain instructions and consult.In the period prior to June 30, 2009,
Canada
was focused on its defence and had to seek an extension of time to comply with its obligations to produce it within the time limits ordered by the Court.The plaintiffs were well aware of
Canada
’s intentions, the jurisdictional issues, and the choices to be made by
Canada
regarding venue.What is more,
Manitoba
was served with the claim by September 28, 2009, not a great deal of time beyond the deadline for filing the claim of June 30, 2009.
[45]
As to whether the third party claim has merit, Canada need only show that it has an “arguable case”: Maax Bath Inc. v. Almag Aluminum Inc., 2009 FCA 251; Bird v. Salt River First Nation, 2009 FC 25; Spencer v. Canada (Attorney General), 2008 FC 1395. On this standard, and for the following reasons, I am satisfied that
Canada
’s claim does have merit.
[46]
Section 8 of the MNRTA provides that
Manitoba
must pay any sums expended pursuant to the Agreement. Manitoba says this cannot create an obligation to indemnify Canada for damages arising from a failure to fulfill fiduciary, treaty or statutory duties and that those damages are not sums expended pursuant to the Agreement.
Canada
, on the other hand, points out that the Agreement contemplated that
Canada
would pay “capital costs,” which were defined to include compensation for “Indian Lands” injuriously affected.
[47]
Though the plaintiffs’ action is for damages for breach of fiduciary duty, the damages sought are to compensate the plaintiffs for injury to their land, including reserve land and improvements.Arguably this is in respect of injury to “Indian Lands” as defined, and the damages fall within the definition of “capital costs” as defined in the LSCA.These costs, moreover, were intended to be shared by
Ontario
and
Manitoba
, as beneficiaries of the Project.
[48]
Manitoba
also alleges that the third party claim does not have merit because it is limitations barred.
Canada
says that it is inappropriate to raise limitations issues on a preliminary motion.I agree with Canada’s submissions that the effect of a statute of limitation can be determined only after the filing of a defence, either at trial or on a summary judgment motion: Watt v. Canada (Transport), [1998] F.C.J. No. 49 (Q.L.); Kibale v. Canada (F.C.A.), [1990] F.C.J. No. 1079 (Q.L.); Villeneuve v. Canada, 2006 FC 456.That determination requires a factual context and cannot be made on a motion to extend time.It is open to
Manitoba
to raise limitations arguments in its defence.
[49]
I now turn to whether there is prejudice arising from the delay in commencing the third party claim.In my view, the delay was not great, and I do not believe that
Manitoba
will be prejudiced as the renewed proceeding is at an early stage, pleadings having only recently closed.While
Manitoba
will need time to review the documents, it has been in possession of them for some time.Indeed,
Manitoba
is not a stranger to this case.Between 2003 and 2007, although
Manitoba
did not participate in negotiations, it was made aware of the issues in the case and it was kept up to date on the specific claim.
Manitoba
’s lengthy involvement in this case suggests that it will not be prejudiced by having to prepare in the timeframe of a case-managed proceeding.More to the point,
Manitoba
has not made out a case to show that the prejudice to the province, if any, is attributable to the delay in commencing the third party claim.At this juncture, moreover,
Manitoba
is on similar footing with
Ontario
which has only recently been added as a party.
[50]
The plaintiffs also maintain that they will be prejudiced by the addition of a third party.They have already invested substantial time and money in pursuing their claim, since the specific claim was filed in 1985. They say that introducing a third party will inevitably cause further delays.They add that the third party claim being based on the MNRTA, which is not at issue in the main action, will add unnecessary complication and cost, cost being a significant factor for the Indian band.As with
Manitoba
, the plaintiffs suggest that
Canada
’s recourse is to start a separate claim against
Manitoba
in the provincial court.
[51]
I note first
Canada
’s response that it is not expanding the lawsuit far beyond the scope of the plaintiffs’ claim. In their amended statement of claim, the plaintiffs pled most of the facts relevant to the third party claim: the LSCA and the Agreement; the definition of “capital costs”; the costs splitting agreement between
Canada
and
Ontario
and the negotiations between
Canada
and
Ontario
in the 1940s on compensating the plaintiffs.
[52]
In addition, says
Canada
, the main issue on the third party claim is a question of law about the interpretation of the LSCA and MNRTA. It may not require the parties to bring much additional evidence or to prove many additional facts which might slow down the proceedings.The point is worth noting as
Manitoba
may choose not to defend against the plaintiffs.
[53]
While the addition of
Manitoba
will add some delay and complication, it will be only incremental to the delay and complexity that the addition of
Ontario
brings to the litigation.Indeed this is one of two important factors that distinguish this case from the circumstances in Fairford First Nation v.
Canada
(Attorney General), [1995] F.C.J. No. 1227 (T.D.) (Q.L.), in which Justice Gibson found prejudice to the plaintiffs sufficient to preclude a third party claim from going forward.Also, in that case, discovery had already been ongoing for 20 days while here, discoveries though in the planning stage, have not yet started.
[54]
I would also point out, as I did with respect to Manitoba’s prejudice arguments, that the added complexity and costs cannot be said to be attributable to Canada’s delay in bringing its third party claim.The plaintiffs would have had to bear the same burden, unwelcome though it may be, if the third party claim had been served some three months earlier, in accordance with the Rules.
[55]
In the circumstances, I conclude that it would be in the interests of justice to grant
Canada
an extension of time to issue and serve its third party claim.
Canada
has an arguable case on the merits and a continuing intention to pursue the third party claim.The prejudice that accrues by way of complexity and delay is merely incremental to the late addition of
Ontario
as a party to the action.More to the point, it cannot be said to have resulted from the delay in commencing the action against
Manitoba
.
[56]
Though the relationships and grievances between the parties are longstanding, the litigation, as I have said, has more recently been renewed.It is, in my view, in the interest of the parties, and of judicial economy, that the issues arising from this litigation be adjudicated together, in the same venue, without further unnecessary proliferation of litigation.That said, every effort will be made in the context of case management to promote the expeditious and least costly prosecution of the plaintiffs’ claims.
Conclusion
[57]
A separate order will issue granting Canada’s motion for an extension of time to issue a third party claim against Manitoba without prejudice to any defences Manitoba may assert, with costs of the motion to be borne by Canada and payable to the plaintiffs and Manitoba, in any event of the cause.
“R. Aronovitch”